Maintain a project invoice plan

Related topics

You can add, remove or change the invoice lines, but the total sum must always equal the invoice plan amount.

  1. Access the invoice plan either on header or phase level. (See Add an invoice plan to a project header or Add an invoice plan to a project phase).
  2. On Project invoice plan maintenance, Order or Project phase inv plan maintenance, Order you can maintain the invoice plan in the following way:
    • Click Add to add a new line to the invoice plan.
    • Select a line and click Delete to remove the line from the invoice plan.
    • Change the date, amount or percentage of an existing invoice plan line.
    • Select a line and click Text to enter free text to be printed on the invoice.

    Note: The total sum of the invoice lines must be 100%, or equal to the invoice plan amount. For this reason, if you delete or add a line you must change the amounts for the remaining lines, or add/delete more lines, so that the total sum is correct.

Exit the routine.

Related topics