Capacity clearance enquiry, Op times in decimal/minutes (PRO023F)

The purpose of this program is to view capacity clearance either for a selected item or a manufacturing order. If the clearance is made for an item, the operation planning is made as a forward planning starting from today’s date. The purpose is also to find out when it is possible to deliver a requested item and quantity (if the production starts today). The best date for production and delivery is displayed.

Options

Workload Select this option to view workload details.
Tool allocation Select this option to view allocations for the included tool(s). Note: This information can only be accessed if the DC1 Tools and fixtures functionality is activated in Work with companies and if at least one tool is connected to an operation.

Function keys

Material View the material clearance.
Minutes/Decimals Toggle between hours and minutes and hours and decimals for the operation times.
Time axis View the time axis for the produced item.
Prev level Only used if you are viewing lower levels. Return to the previous level.

Selection fields

Item
Warehouse
Variant
Quantity
Start date
This field is only displayed if clearance is made for a manufacturing order.
Compl date
This field is only displayed if clearance is made for a manufacturing order.
Order number
This field is only displayed if clearance is made for a manufacturing order.

Op no
Description
Work centre
Start date
Compl date
Required time
The operation time that is used for workload planning.
Cap date
The first date where capacity exists to cover the needed operation time. This is only calculated if shortage exists. If only critical resources should be handled, this date will be blank even though there might be a shortage of capacity.
S
The code indicates if shortage exists for the operation. Note: If there is any shortage, an asterisk is displayed next to the operation that is most critical, i.e. that has the highest number of shortage days.

Valid codes are:

Code Description
0 No capacity problems
1 Capacity shortage
2 Tool shortage
3 Both capacity shortage and tool shortage exist for the operation.
Text
Indicates if tools are connected to the operation.