1. Home
  2. /
  3. Panel Help
  4. /
  5. Manufacturing
  6. /
  7. Manufacturing history enquiry, Bill...

Manufacturing history enquiry, Bill of routing (PRO205E)

In this enquiry you can view the manufacturing order history, bill of routing information.

Options

Function keys

Item
Warehouse
Variant
Item version
Order number
Order type
Order qty
Reported qty
The total quantity reported.
Pln start
This field also displays the time when the order is planned to be started. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
Act start
This field also displays the actual start time of the order. Note: The time textbox is only displayed if the function MPL-TIME (plan operation by date/time) is activated in the Function control file.
Dly days
The number of days delayed between the actual start date and the planned start date.
Pln compl
This field also displays the time when the order is planned to be completed. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
Act compl
This field also displays the actual completion time of the order. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
Dly days
The total number of days delayed between the actual completion date and the planned completion date.
Oper no
Work centre
The work centre where the operation was performed.
Description
The description of the work centre.
Diff amount
The difference in amount between product costing and cost control amount for the operation.
Dly start
The number of days delayed between the actual start date and the planned date for the operation.
Dly compl
The number of days delayed between the actual completion date and the planned completion date for the operation.