In this enquiry you can view the manufacturing order history, bill of routing information.
Options
Function keys
- Item
- Warehouse
- Variant
- Item version
- Order number
- Order type
- Order qty
- Reported qty
- The total quantity reported.
- Pln start
- This field also displays the time when the order is planned to be started. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
- Act start
- This field also displays the actual start time of the order. Note: The time textbox is only displayed if the function MPL-TIME (plan operation by date/time) is activated in the Function control file.
- Dly days
- The number of days delayed between the actual start date and the planned start date.
- Pln compl
- This field also displays the time when the order is planned to be completed. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
- Act compl
- This field also displays the actual completion time of the order. Note: The time textbox is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
- Dly days
- The total number of days delayed between the actual completion date and the planned completion date.
- Oper no
- Work centre
- The work centre where the operation was performed.
- Description
- The description of the work centre.
- Diff amount
- The difference in amount between product costing and cost control amount for the operation.
- Dly start
- The number of days delayed between the actual start date and the planned date for the operation.
- Dly compl
- The number of days delayed between the actual completion date and the planned completion date for the operation.