The purpose of this program is to re-schedule manufacturing orders with finite capacity. The program can be executed in mode for only produced reports with new calculated start and completion date (open manufacturing orders with a work centre defined as a critical resource) or executed in mode for re-schedule of the orders. The mode is determined by what has been entered in the Re-schedule orders field.
Note: Manufacturing order operations that have been started (operation status 40) or manufacturing order operations that have been locked will not be included in the re-schedule calculation.
- Main sort sequence
- The code indicates how the manufacturing orders should be sorted.
Code Description 1 Sort by planned start date for the manufacturing order operations. 2 Sort by planned start week for the manufacturing order operations. 3 Sort by original planned start date for the manufacturing order operations. 4 Sort by original planned start week for the manufacturing order operations. 5 No main sort sequence. All operations will get the same value.
- Sequence
- The sequence 1, 2, 3 or 4, indicates how the information should be organised. Enter 1 for primary sort order. Enter 2 if you want to sort the information further within each parameter selected with sequence 1, etc.
- Sales orders
- Prod technology
- Operation priority
- Operation sequence
- Sales order value
- The code indicates the value that should be used for sequence sorting when sales order has been selected in the sequence fields.
Code Description 1 Sales order priority 2 Profit value 3 Invoiced amount
- Warehouse
- Work centre
- First schedule date
- The date indicates the first possible planning date for the orders in the critical work centre. The orders will be re-scheduled starting from the entered date.
- Pln start horizon
- The horizon date to be used as a selection for which manufacturing order operation (planned start date) to be included in the re-schedule.
- Re-schedule orders
- Indicates if the manufacturing order should be re-scheduled or if only a control list should be produced with the new calculated planned start and completion date.
- Lock operation
- Indicates if the operations should be locked after the re-scheduling of the manufacturing orders. This is only allowed if Re-schedule orders is set to YES.
- Print control list
- Indicates if a control list, showing the changes, should be printed with the new calculated start and completion dates.
- Only changed orders
- Indicates if only those orders that actually have been re-scheduled or are to be re-scheduled (depending on what was specified in the Re-scheduled orders field above) should be printed.