The purpose of this program is to display all equations that have been performed and calculated for selected operation number from the Product costing bill of routing overview.
Options
- Item
- Calc date
- The date indicates when the right prices and overhead were retrieved.
- Cost model
- The cost model id used for product costing.
- W c price
- The code indicates from where the work centres prices have been retrieved during the product costing calculation.
Code Description 1 Standard 2 Actual 3 Simulation
- Std quant PC
- The quantity in stock unit the product costing is based on.
- Struct quant
- Variant
- Warehouse
- Struct unit
- Operation no
- Work centre
- Line
- The line identity for cost model equation line.
- Tool
- This field is only displayed if the DC1 Tools and fixtures functionality is activated in Work with companies. This is the code that identifies the tool for the calculated cost. If this field is left blank the calculation is based on operation values.
- Description
- The description of the equation.
- Amount
- The calculated amount for the equation line.