Manufacturing order network re-schedule (PRO004C)

This panel is displayed when an order/operation has been re-scheduled from detail planning and the order/operation is included in manufacturing order network. This panel gives you the possibility to re-schedule the other orders based on the re-scheduled order/operation.

Main order
Indicates if the order/operation are included in a manufacturing order network.
Reschedule
Set this field to YES if the order network should be re-scheduled.