This panel displays a summarised enquiry of the work centres connected to an item structure. The enquiry displays, per set-up time (int/ext), run and labour time and machine time, the total amount of hours the work centres are occupied.
Function keys
Print the enquiry. |
- Customer
- Project
- Phase
- Line number
- Item
- Work centre
- The operation times are summarised per work centre.
- Description
- Set-up int
- The total internal set-up time for the work centre.
- Set-up ext
- The total external set-up time for the work centre.
- Run and labour
- The total run and labour time for the work centre.
- Machine
- The total machine time for the work centre.