Accept a project element structure

Related topics

  1. Select the Work with projects menu item.
  2. You access Work with project orders. Select the project you want to work with and click Details.
  3. You access Phase maintenance. Select the phase to which you want to add a structure and click Elements. (Tip: You can also access the element level of the project by clicking the Level function key on the initial Work with project orders panel and then selecting the Element level).
  4. You access Phase element maintenance. Select the element line to which you want to add operations and click Struct.
  5. You access Structure maintenance. Click the Accept structure function key. The structure of the material line is now accepted and no further changes can be made to the structure. Exit the routine.
  6. Tip: Click the Cancel acceptance function key to make it possible to maintain the project structure again.

Related topics