If you do not wish to re-schedule or delete an order you can omit the re-scheduling. This means that the manufacturing or purchase order is accepted without changes, and that re-scheduling will never again be proposed for the order. If there are other orders where the requirement date is less than or equal to the omitted order’s requirement date, each order will be indicated as automatically ignored, i.e. accepted without any action taken. Note: Only orders indicated for backward re-scheduling will be indicated as automatically ignored.
- Select the Work with MRP (Manufacturing) or Work with MRP (Purchase) menu item.
- You access Work with MRP manufacturing or Work with MRP purchase respectively. Select the proposal that is indicated for re-scheduling and click Re-schedule.
- You access MRP re-schedule proposal maintenance. Select the re-schedule proposal and click Omit re-schedule to remove the re-scheduling of the proposal. Exit the routine.
Related topics
- About material requirements planning (MRP)
- Calculate material requirements planning (MRP)
- Manually mark an MRP order proposal for release
- Automatically mark MRP order proposals for release using batch job
- Automatically release MRP order proposals using batch job
- Manually release an MRP order proposal
- Re-schedule an order created from an MRP order proposal
- Simulate MRP and access the calculated simulation