Project transactions report (POM013A)

The purpose of this program is to select printing of issues for activities, services and items that have not been invoiced or delivered, or to select printing of not closed element lines for which it is possible to report issues.

Project
The project interval to be printed.
Phase
The phase interval to be printed.
To date
Mandatory entry. The date indicates the end of the period for which transactions or element lines are to be printed. The Type of transactions field determines what transactions will be printed. If 1, 2 or 3 is selected, a list of project transactions is printed according to transaction date. If 4 is selected, a list of open element lines is printed according to dispatch date.
Type of transactions
Mandatory entry. The code indicates the type of transactions to be printed. The transaction type refers to the invoice indication on the transactions.

Valid codes are:

Code Description
1 Transactions that are to be invoiced are printed.
2 Transactions that are to be delivered are printed.
3 Both invoicing and delivery transactions are printed.
4 Open element lines that are not linked to acquisition orders are printed.
Element type
The code indicates the the project element type.

Valid codes are:

Code Description
1 Line (= Item)
2 Service
3 Activity
Cost code
The cost code interval to be printed. Refers to the first cost code on the element line.
Handler