Related topics
This program is used to report start and stop for project activities. In Work with attesting this program is used only to report start of an activity.
- Employee
- Date
- Displays the date for start or stop.
- Time
- Displays the time for start or stop.
- Stop project
- This text is only shown if you have an ongoing project activity. The activity will be stopped when you click OK.
- Invoice
- Only shown if you have an ongoing activity for a project in DC1 Project and if it is allowed to change the invoicing code. Indicate if the hours are to be invoiced.
- Project activity
- Only shown if DC1 Project is installed and activated in the company in which you are working. If you want to start a new project activity, enter the code for the activity. Entered value must be the key of an existing project activity.
- Project
- Not shown if DC1 Project is installed and activated in the company in which you are working. Enter a code from Work with projects. The selected project must be active, i.e., the booked date must be within the defined start and end date of the project.
- Cost centre
- Enter a code from Work with cost centres, if the activity is to refer to a cost centre.