Operation detail maintenance, Op times in decimal/minutes (POM060J)

Related topics

The purpose of this program is to maintain operation detailed information.

Function keys

Minutes/Decimals Toggle between hours and minutes and hours and decimals for the operation times. Note: This function key is not allowed when the program is in Add mode.
Cost price information Maintain operation hour prices.
Customer
Project
Status
The code indicates the status of the project/quotation.

Valid codes are:

Phase
Line
The number and description of the element line being maintained.
Item
The item being maintained.
Operation number

Work centre
Time basis code
Run and labour time
Set-up time int
The internal set-up time in hours for the operation. This time is used as a part in the Project/quotation costing calculation function in combination with the operation hours costs.
Set-up time ext
The external set-up time in hours for the operation. This time is used as a part in the Project/quotation costing calculation function in combination with the operation hours costs.
Machine time
The machine time in hours for the operation. This time is used as a part in the Project/quotation costing calculation function in combination with the operation hours costs.
Waste percentage
Reporting operation
Indicates if this operation should be reported on the manufacturing order. If NO, the operation times will be backflushed when the next operation is reported. This means that by setting reporting points at certain operations the system will back-flush the reporting for all operation from present operation to the previous reporting operation (milestone).
Reporting calc
This field can only be used if the operation is defined as a reporting operation. This field is used to calculate run/labour, machine or approved quantity at manufacturing order operation reporting within manufacturing. Note: This field overrides the value entered at work centre level. The field after the input field displays the value from the work centre. The code indicates the type of calculation that should be used for this work centre.

Valid codes are:

Code Description
1 No suggestion calculated
2 Time will be calculated
3 Approved quantity will be calculated
Resources per job
The number of resources to be used for this operation. This information is used to calculate the time per day that a manufacturing order operation can be planned. Note: The value entered in this field overrides the value from the work centre level. The field after the input field displays the value from the work centre.
Tool 1 – 2
This field is only displayed if the DC1 Tools and fixtures functionality is activated in Work with companies and denotes the tools that are connected to the current operation.
Valid from
The dates indicate the period during which the operation should be active in the system. At e.g., manufacturing order creation, the validation of the operation should be copied to the manufacturing order, which is made on the creation date.
Overlapping type
The code defines the overlapping to the previous operation. to define overlapping to the previous operation. This type is, in combination with the overlapping value, used to calculate operation planning dates overlapped in the Manufacturing order, MRP and Capacity clearance functions.

Valid codes are:

Code Description
1 Quantity
2 Percentage of workload time
Overlapping value
The overlapping value (quantity or percentage) to define overlapping to the previous operation. Mandatory entry in combination with the overlapping type.
Queue time
The queue time for this operation that is used as the time before starting current operation. If queue time is entered this is a override value from work centre.
Transport time
The transport time for this operation that is used as a time after completion of current operation. If transport time is entered this is a override value from work centre.
Prod technology
The production technology code can be used as a base operation detail planning in the manufacturing order module to set the base run priority.
Subc operation
This field is only displayed if the DC1 Manufacturing sub-contractor functionality is activated in Work with companies. Indicates if a purchase order should be created from the manufacturing order for current operation.