Copy an element line in a project phase

Related topics

  1. Select the Work with projects menu item.
  2. You access Work with project orders. Select the project you want to work with and click Details.
  3. You access Phase maintenance. Select the phase for which you want to copy an element and click Elements. (Tip: You can also access the element level of the project by clicking Level on this panel and selecting the Element level).
  4. You access Phase element maintenance. Select the element line you want to copy and click Copy.
  5. You access Phase element maintenance, Copy. Complete the following fields:
  6. Phase element text
    Indicate if the phase element text should be copied to the new element line.
    Structure
    Indicate if the phase element structure should be copied to the new element line.

    Click OK to process the copying. Exit the routine.