Work with work centre scheme groups (BAS023A)

This program is used to create a new scheme group or modify an existing group. Besides this, an enquiry can also be made to determine in which work centre the scheme group has been attached to.

Note: To run this program the MPL-TIME (Plan operation by date/time) function is activated in the Function control file. Otherwise, the system will generate an error message.

Options


Note: This option is not allowed if a scheme group is used in at least one work centre.

Where used Select this option to display in which work centre(s) the selected group code has been used.

Selection fields

Group
Indicates the group code for the work centre scheme group.
Description
The description of the work centre day scheme group.