The reduction of capacity is restricted to work centres for which the Workl planning type field is set to 2 (machine) and the Number of machines field is set to 1.
Note: If you have changed the preventive service information or the kit specification and the work centre capacity has been reduced, you must manually undo the reduction (click Undo reduction) and then reduce the work centre capacity again so that it reflects the new service time.
To reduce the work centre capacity with the planned preventive service time defined by the kit specification for the service object do as follows:
- Select the Work with service objects menu item.
- On the initial panel, select the applicable service object and click Prev service.
- You access Work with service objects, Preventive service information. Click Preventive service calendar.
- You access Work with service objects, Preventive service calendar. Select a date and click Reduce capacity. The following fields are updated:
- Service time
- Displays the calculated service time according to the kit specification for the preventive service object.
- Reduce
- Has been set to YES indicating that the work centre capacity has been reduced by the service time.
Exit the routine.