This panel displays the existing SOP base resources. The resources (employees, machines etc.) are used in the calculation of the resource capacity and the production efficiency for the sales and operation plan.
If the base resources should be used in an SOP, they must first be connected to a key value (item group, item family, item sector or department section) and a key value id in Work with SOP resources. Depending on the key value id’s that are used in the sales and operation plan, the corresponding SOP base resources will be connected to the SOP in question.
- Resource
- The code that identifies the resource. This may, for example, refer to a group of employees, machines, robots etc.
- Description
- The description of the resource.
- Unit
- The resource unit.
- No of dec
- The number of decimals to be used for the resource quantity. Valid number of decimals is 0-3.