1. Home
  2. /
  3. Panel Help
  4. /
  5. Manufacturing
  6. /
  7. Work with structures, Mass-update...

Work with structures, Mass-update BOM/BOR (BAS003F)

On this panel you define the component, component quantities, work centre, operation times or tool that should be updated, exchanged or deleted in the item structures. Using the available selection fields, you can also limit the number of item structures to be processed.

Depending on the type of mass-update you have selected, different fields are available on this panel. Click the links below for information about the fields that are displayed for the different updates:

Exchange components

The following fields must be completed when you have selected to exchange components:

Component
The component that should be exchanged in the selected item structures.
New component
The component that should replace the selected item in the selected item structures.

Delete components

The following field must be completed when you have selected to delete components:

Component
The component that should be deleted from the selected item structures.

Update component quantities

The following fields must be completed when you have selected to update component quantities:

Component
The component that should be updated with a new quantity in the selected item structures.
New quantity
The new quantity for the selected component.

Exchange work centres

The following fields must be completed when you have selected to exchange work centres:

Work centre
The work centre that should be exchanged in the selected item structures.
New work centre
The new work centre that should replace the work centre in the selected item structures.

Delete work centres

The following field must be completed when you have selected to delete work centres:

Work centre
The work centre that should be deleted from the selected item structures.

Update operation times

The following fields can be completed when you have selected to update operation times (not all operation times must be changed at the same time):

Work centre
The work centre that should be updated with new operation times in the selected item structures.
New run/labour time
The new value that will replace the run/labour time for the selected work centre in the bill of routing.
New machine time
The new value that will replace the machine time for the selected work centre in the bill of routing.
New set-up time int
The new value that will replace the internal set-up time for the selected work centre in the bill of routing.
New set-up time ext
The new value that will replace the external set-up time for the selected work centre in the bill of routing.

Exchange tools

The following fields must be completed when you have selected to exchange tools:

Tool
The tool that should be exchanged in the selected item structures.
New tool
The new tool that should replace the tool in the selected item structures.

Delete tools

The following field must be completed when you have selected to delete tools:

Tool
The tool that should be deleted from selected item structures.

Selection

  • Item
  • Item group
  • Item family
  • Item sector
  • Department section
  • Item type
  • Item class
  • Warehouse
    Note: This field is only displayed when the Whs in BOM field is set to YES in the MFG control file.
  • Variant
    Note: This field is only displayed when the Variant handling field is set to YES in the MFG control file.
  • Work centre
    Note: This field is only displayed if you have selected to update tools.