The purpose of this program is to select a part of a lead time proposal to be updated in the Item file. Note: The items that are not selected for update will not be deleted from the proposal. It is possible to run this update function several times for a proposal.
- Proposal
- The number and description of the proposal.
Selection
- Planner
- Item group
- Item family
- Item sector
- Department section
- Item type
Valid intervals are 1-2. - Item class
Valid intervals are 1-4. - Warehouse
- Item
- Lead time update
- This field is only displayed if Lead time calc is set to 2 or 3 on the Lead time proposal creation panel. The code indicates what fields should be updated in the Item file.
1 Production lead time 2 Lead time 3 Both production lead time and lead time
- Update on
- The code indicates on which level the new lead time should be updated.
1 Item level 2 Item and warehouse level