Cumulative operation enquiry, Op times in decimal/minutes (BAS038D)

This panel displays a summarised enquiry of the work centres connected to an item structure. The enquiry displays, per set-up time (int/ext), run and labour time and machine time, the total amount of hours the work centres are occupied.

Function keys

Minutes/Decimals Toggle between hours and minutes and hours and decimals for the operation times.
Print Print the enquiry.
Item
Warehouse
Variant
Structure quantity
Work centre
The operation times are summarised per work centre.
Description
Set-up int
The total internal set-up time for the work centre.
Set-up ext
The total external set-up time for the work centre.
Run and labour
The total run and labour time for the work centre.
Machine
The total machine time for the work centre.