1. Home
  2. /
  3. Panel Help
  4. /
  5. Manufacturing
  6. /
  7. Work with master BOR,...

Work with master BOR, Bill of routing, op times in minutes/decimal (BAS061A)

The purpose of this program is to maintain operations attached to the master BOR. From this panel you can access functions to create and maintain operations and related information.

Options

Tool Access the Work with master BOR, Tool/fixture panel where you can maintain master information for the bill of operation tools.

Function keys

Add Add a new record.
Minutes/Decimals Toggle between viewing operation times in minutes and decimals.
Op renumbering Access the Operation number renumbering panel where you can renumber the operations for the selected master BOR.
BOR id
The code that identifies the Master BOR, and the description.
Structure quantity
In add mode, this field is defaulted with 1. If the Master BOR has already been used in the structure header, this field is output only.

Enter/change the structure quantity. This quantity indicates the relationship between the structure quantity and the component quantities/operation times.

The structure quantity can be used to adjust the operation times in order to avoid short times in the bill of routing.

If the structure quantity is changed, meaning that the component quantity is also changed, then the run, labour and machine time must be adjusted accordingly.

Structure unit
The structure unit of the item. See Structure unit handling for more information.
Op no
The operation number that is registered in intervals of 10 indicates the order in which the operations are displayed.
Description
The description of the operation.
Work centre
The work centre where the operation is to be performed.
TB-code
The time basis code indicates in what size the operation time is entered. If this field contains information, it will override the structure quantity.

Valid values are:

Value Description
*Blank Times according to the structure quantity.
1 Times per 10 units.
2 Times per 100 units.
3 Times per 1000 units.
4 Times per 10000 units.
Run and Labour time
The run and labour time in hours for the operation. The run and labour time is used in the product costing calculation in combination with the work centre hour costs. This information is also used in the planning function of the calculated workload, i.e. workload, preliminary workload and planned workload.
T