Related topics
This panel displays all MRP planned items, i.e the items that are defined with Planning method set to 2 (MRP) in the Item file. The First prop field on this panel indicates for which items production proposals have been created through the MRP calculation. You can maintain, release mark and release the calculated proposals. You can also reschedule manufacturing orders that have been created from a proposal.
Options
Proposal |
Select this option to maintain order proposals. |
Pegging |
Select this option to view the MRP result of an item. |
Re-schedule |
Select this option to maintain orders that have been indicated for re-scheduling. The Re-sch field indicates that reschedule proposals exist for the item line. |
Function keys
Full mode resch |
Maintain all orders that have been indicated for rescheduling. Working in full mode, all existing reschedule proposals are accessed in the same panel. |
Select/delete sim |
Select or delete a simulation version. |
Active ver |
Work with the active version. |
Selection fields
- Planner
- The code indicates the planner of the item.
- Item/Description
- Pri
- This field is only displayed if Manufacturing finite planning (MFP) is activated. The code indicates the priority for the highest prioritised proposal with a start date less than the item’s lead time.
Valid codes are:
Code |
Description |
01 |
Based on sales order |
02 |
Based on sales order and manufacturing order |
03 |
Based on sales order and forecast |
04 |
Based on sales order and sales quotation |
05 |
Based on project |
06 |
Based on manufacturing order and forecast |
07 |
Based on manufacturing order and sales quotation |
08 |
Based on manufacturing order |
09 |
Based on forecast |
10 |
Based on forecast and sales quotation |
11 |
Safety stock |
12 |
Based on sales quotation |
30 |
Quantity on hand |
- Whs
- The warehouse where the item is produced.
- First prop
- The first generated order proposal start date.
- P D
- This field is only applicable for order proposal. Order proposal include demand in passed time. If the order proposal is based on demand in passed time this field is set to YES.
- Re-sch
- Indicates if a proposal to re-schedule the item exists.