Related topics
This panel displays the product costing and cost control values from the manufacturing order that is connected to the project element line.
Function keys
- Order number
- The project, phase number, line number and phase description.
- Description
- The description of the different costing values that can be displayed for the element:
- Total manufacturing cost
- Component cost
- Run labour/machine cost
- Component cost TL (this level)
- Run labour/machine cost TL (this level)
- Manufacturing cost LL (lower level)
- Component cost LL (lower level)
- Run labour/machine cost LL (lower level)
- Run labour time TL (this level)
- Machine time TL (this level)
- Run labour time LL (lower level)
- Machine time LL (lower level)
- Product costing
- The product costing values for the element.
- Cost control
- The cost control values for the element.
- Difference
- The difference between the product costing and the cost control values.
- Run labour time (override)
- In Total cost mode, the run labour time that overrides the calculated values that are displayed in Run labour time TL/LL.
- Machine time (override)
- In Total cost mode, the machine time that overrides the calculated values that are displayed in Machine time TL/LL.