From here you can print a report on the project or quotation (phase) totals. The reports will have a layout which is similar to the layout of the project or quotation (phase) totals enquiries.
- Project no/Quotation no
- Phase
- The phase interval for printing. If this field is left blank, all phases on selected project/quotation are printed.
- Cost code
- The cost code interval for printing. If this field is left blank, all cost codes on selected project/quotation are printed.
- Tot phase
- Indicates if the totals on phase level should be printed.
- Tot cost code
- Indicates if the totals on cost code level should be printed.
- Tot phase/cost code
- Indicates if the totals on phase/cost code level should be printed.
- In system currency
- Indicates if the printing of the values is to be in system currency. If this field is set to NO, the printing will be in project currency.
- Detailed info
- Indicates if the element lines per phase should be printed.