From here you can print a report on the project or quotation (phase) totals. The reports will have a layout which is similar to the layout of the project or quotation (phase) totals enquiries.

Project no/Quotation no
Phase
The phase interval for printing. If this field is left blank, all phases on selected project/quotation are printed.
Cost code
The cost code interval for printing. If this field is left blank, all cost codes on selected project/quotation are printed.
Tot phase
Indicates if the totals on phase level should be printed.
Tot cost code
Indicates if the totals on cost code level should be printed.
Tot phase/cost code
Indicates if the totals on phase/cost code level should be printed.
In system currency
Indicates if the printing of the values is to be in system currency. If this field is set to NO, the printing will be in project currency.
Detailed info
Indicates if the element lines per phase should be printed.