Cumulative structure enquiry (POM064C)

Related topics

The purpose of this program is to plan purchase for a produced item with large structures. The cumulative structure displays a cumulative need for all material in the structure down to the lowest level.

Options

Purchase Select this option to create a purchase requisition.
Time axis Select this option to view the time axis.

Function keys

Operations View a summarised enquiry of the bill of routing. The enquiry displays, per set-up time (int/ext), run and labour time and machine time, the total amount of hours the work centre is occupied.
Print Print the enquiry.
Customer
Project
Phase
Line number
Item
Component item
Whs
Quantity
The total requirement for the parent item.
Unit
The stock unit for the component item.
Quantity on hand
The quantity on hand for the component item in the allocation warehouse.