On this panel you can view the operation structure detailed information.

Function keys

Minutes/Decimals Toggle between hours and minutes and hours and decimals for the operation times.
Cost price information View operation hour prices.
Customer
Project
Status
The code indicates the status of the project/quotation.

Valid codes are:

Phase
Line
Item
The code that identifies the item and variant.
Operation number
Work centre
Time basis code
Run and labour time
The run and labour time in hours for the operation, i.e. the actual time spent on the operation. This time is used as a part in the Project product costing calculation function in combination with the operation hours costs which is displayed in the cost price information panel (F8).
Set-up time int
The internal set-up time in hours for the operation. This time is used as a part in Project/quotation costing calculation function in combination with the operation hours costs, which is displayed in the cost price information panel (F8).
Set-up time ext
The external set-up time in hours for the operation. This time is used as a part in Project/quotation costing calculation function in combination with the operation hours costs, which is displayed in the cost price information panel (F8).
Machine time
The machine time in hours for the operation. This time is used as a part in Project/quotation costing calculation function in combination with the operation hours costs, which is displayed in the cost price information panel (F8).
Waste percentage
Reporting operation
Indicates if the operation should be reported on manufacturing order. If this field is set to NO, the operation times will be backflushed when the next operation is reported. This means that by setting reporting points at certain operations the system will back-flush the reporting for all operation from present operation to the previous reporting operation (milestone).
Reporting calc
This field is used to calculate run/labour, machine or approved quantity at manufacturing order operation reporting within manufacturing. The code indicates the type of calculation that is used for this operation.

Valid codes are:

Code Description
1 No suggestion calculated
2 Time will be calculated
3 Approved quantity will be calculated

Note: If two values are displayed, the left field displays the value entered for the BOR and the right field displays the value entered for the work centre.

Resources per job
The number of resources to be used for this operation. This information is used to calculate the time per day that a manufacturing order operation can be planned. Note: The value entered in this field overrides the value from the work centre level.
Tool 1 – 2
This field is only displayed if the DC1 Tools and fixtures functionality is activated in Work with companies. Displays the tools that are connected to the operation.
Valid from
The start date and the end date of effect when an operation can be included and excluded as a component in the operation list. Before the start date and after the end date the operation will not be used.
Overlapping type
Displays 1 (quantity) or 2 (percentage of workload time) to define overlapping to the previous operation. This type is, in combination with the overlapping value, used to calculate operation planning dates overlapped in the following functions: Manufacturing order, MRP and Capacity clearance.
Overlapping value
The overlapping value (quantity or percentage) defines the overlapping to the previous operation. This field is used in combination with Overlapping type.
Queue time
The queue time in hours for the operation that is used as the time before starting current operation.
Transport time
The transport time in hours for this operation that is used as a time after completion of current operation.
Prod technology
The production technology code can be used as a base operation detail planning in the manufacturing order module to set the base run priority.
Subc operation