Note: The supply values cannot be changed if lower level requirements have been calculated for the item.
- Select the Work with supply plans (SP) menu item.
- On the initial panel, click Details.
- You access Work with supply plan, Items listing those items for which Supply plan is set to YES in the Item file. Select the applicable item/warehouse combination and click Details.
- You access Work with supply plan, Period details. Select the period you want to maintain and click Change.
- On the Work with supply plan, Period details detail panel you can change the following field:
- Supply
- Enter the suggested quantity for supply.
Click OK. You return to the previous panel where the new suggested quantity is displayed in Supply qty. Exit the routine.
Related topics
- About supply planning
- Create the base supply plan version
- Create a supply plan simulation
- Calculate the supply plan values
- Calculate lower level requirements from supply plan
- Run the IC calculation from the supply plan program
- Create orders from a supply plan
- View the safety stock calculation for a warehouse in a supply plan
- Formula for safety stock calculation in a supply plan