You can replace the already created scheme(s) for the day or override the man factor and/or number of machines in order to decrease the capacity when a person (employed in work centre) is not available.
- Select the Work with work centres menu item.
- You access Work with work centre. Select the applicable work centre and click Change capacity.
- You access Work centre capacity maintenance, Capacity in decimal (minutes). Select the date for which you want to create the scheme and click Schemes.
- You access Work centre capacity maintenance – Scheme in add mode. Complete the following field:
- Day scheme
- Enter the day scheme for the selected working day. The day scheme consists of a mandatory part defining working hours and breaks. The optional part consists of man factor and number of machines.
See the Panel help for information about the remaining fields.
Click OK. The day scheme detail, for the selected day, is added for the work centre. Exit the routine.
Related topics
- About work centres
- Create a work centre
- Create work centre capacity
- Change the capacity for a work centre
- Change the work centre parameters
- Create the day scheme to be attached to a work centre
- Create work centre scheme groups
- Attach a day scheme to the working days in a work centre
- Set up a workload restriction group
- Add workload restrictions to a work centre
- Create a work centre capacity simulation version
- Simulate the capacity for a work centre
- Activate future work centre prices
- Delete a work centre