Change the forecast for a project budget

Related topics

The forecast is specified per cost code.

  1. Select the Work with projects menu item.
  2. You access Work with project orders. Select the project to which you want to add a budget and click Budget.
  3. You access Budget maintenance. Complete the following fields:
  4. Reason for change
    Enter a text indicating the reason for changing the budget figures. The text is saved in the Budget history file.
    Forecast
    Enter a forecast for one or several cost codes. The total forecast for the project is displayed in the Tot Proj/Forecast field.

    Click OK to update the changed budget. The changes can be viewed in the Project budget history enquiry. Exit the routine.