The forecast is specified per cost code.
- Select the Work with projects menu item.
- You access Work with project orders. Select the project to which you want to add a budget and click Budget.
- You access Budget maintenance. Complete the following fields:
- Reason for change
- Enter a text indicating the reason for changing the budget figures. The text is saved in the Budget history file.
- Forecast
- Enter a forecast for one or several cost codes. The total forecast for the project is displayed in the Tot Proj/Forecast field.
Click OK to update the changed budget. The changes can be viewed in the Project budget history enquiry. Exit the routine.